(4 tussenliggende versies door 3 gebruikers niet weergegeven) | |||
Regel 8: | Regel 8: | ||
|Heading nl=Designing and researching ecoblock revetments |
|Heading nl=Designing and researching ecoblock revetments |
||
|Heading en=Designing and researching ecoblock revetments |
|Heading en=Designing and researching ecoblock revetments |
||
+ | }} |
||
+ | {{Paragraph |
||
+ | |Paragraph number=1 |
||
+ | |Paragraph language=Dutch-English |
||
+ | |Paragraph=The research and design of the revetment was achieved in two phases. The first phase comprised a literature study of similar projects, see {{Internal link|link=Bfn Literature review and interviews ecoblock revetments VN|name=this page}}. This literature study is used as input for the second phase and also on the methodology to evaluate the results. In the second phase workshops were organized with a group of experts with different backgrounds to analyze and define the final designs. The revetment blocks were later applied in the intertidal zone on a frame (Yerseke) and at a dyke revetment (Sint Annaland site). |
||
+ | |||
+ | For an overview of the ecological developement at the Dike at Sint-Annaland see {{Cite|resource=Building for Nature - video |name=this video}}<br/> |
||
+ | Omroep Zeeland made a news item (in Dutch) about the ecological developments of the dikes: {{Cite|resource=Geen grijze dijken meer, maar groene|name= see here}}. |
||
}} |
}} |
||
<imagemap> |
<imagemap> |
||
Regel 30: | Regel 38: | ||
rect 63 70 1045 1858 [[Bfn Building for Nature project]] |
rect 63 70 1045 1858 [[Bfn Building for Nature project]] |
||
</imagemap> |
</imagemap> |
||
− | |||
− | |||
{{VN query}} |
{{VN query}} |
||
{{Activity links |
{{Activity links |
Bfn Designing and researching ecoblock revetments | |
---|---|
Context | Bfn Building for Nature project |
Decompositie type | IOR |
Activity
The research and design of the revetment was achieved in two phases. The first phase comprised a literature study of similar projects, see this page. This literature study is used as input for the second phase and also on the methodology to evaluate the results. In the second phase workshops were organized with a group of experts with different backgrounds to analyze and define the final designs. The revetment blocks were later applied in the intertidal zone on a frame (Yerseke) and at a dyke revetment (Sint Annaland site).
For an overview of the ecological developement at the Dike at Sint-Annaland see this video
Omroep Zeeland made a news item (in Dutch) about the ecological developments of the dikes: see here.
De View-Navigation (VN) pagina's.
De links naar andere pagina's.
Produceert | |
---|---|
Consumeeert | |
Onderdeel van | Bfn Researching and designing solid dike revetments to increase natural values |
Instantie van | |
Betreft |
De pagina's die linken naar deze pagina.
Bestaat uit | Type |
---|---|
Bfn Conclusions ecoblock revetments | Outcome |
Bfn Data analysis ecoblock revetments | Activity |
Bfn Data collection ecoblock revetments | Activity |
Bfn Data ecoblock revetments | Outcome |
Bfn Design ecoblock revetments | Outcome |
Bfn Design ecoblock revetments with stakeholders | Activity |
Bfn Knowledge gaps ecoblock revetments | Outcome |
Bfn Literature review and interviews ecoblock revetments | Activity |
Bfn Production and placing ecoblock revetments | Activity |
Naar dit element wordt niet geconnecteerd.